Title

NATIONAL AUDIT OFFICE

Managing the smooth expiry of PFI contracts

Rosie Pearson says the end of a PFI contract may seem a long way off, but contract expiry should be considered at an early stage to ensure that it can be a success.

On 5 June, The MJ reported the release of the National Audit Office's (NAO) report, Managing PFI assets and services as contracts end which was supported by analysis from the Infrastructure and Projects Authority and Local Partnerships.

The end of a PFI contract may seem a long way into the future. However, in the first part of this decade over 50 operational PFI contracts will expire. This number rises to around 200 contracts over the next 10 years.

Dealing with contract expiry can be resource-intensive and will certainly require more support than is currently being provided to the project. A key risk is the increased cost of delivery and potential disruption to services if adequate and appropriate preparation are not put in place well in advance of contract expiry. Issues such as whether services, e.g. maintenance and cleaning, are provided in-house, by a new contractor or through a new contractual relationship with the existing provider must be addressed. If the facility or assets do not revert upon contract expiry, then a decision will be needed as to whether to continue to use them and, if so, what negotiations need to take place.

It is important to understand the timeline to expiry within each contract. A number of the earlier PFI contracts do not specify a timeline at all. Others simply refer to "surveys on expiry", to be commenced two to three years before the expiry date. Infrastructure and Projects Authority guidance suggests starting to prepare seven years from the expiry date. Such preparation should form part of a mid-term contract review, allowing for challenge to the way the contract is currently managed. It will also help the public authority identify any issues which require maintenance to achieve the required standard and what is required from an expiry process.

Any contract should consider three concurrent workstreams:

Even the best providers and authorities with excellent relationships will be confronted by a myriad of issues that will need to be addressed through the process. The resolution and timing of tackling these issues will require careful project planning.

The National Audit Office report surveyed 107 PFI contracts of which 89 were still operational and 18 had expired. The report draws out challenges and best practice. This is a timely report and can be used to raise the profile of this issue within public authorities.

Three key considerations the report highlights are:

  • only a third of respondents thought that the role and obligations of different parties at expiry were clearly defined
  • 55% of survey respondents recognised that they weren't certain about the condition of the assets
  • 33% of survey respondents considered that disputes near contract end are likely, with 86% of disputes expected to relate to the quantity of rectification work

Contract expiry should be considered at an early stage – ideally well in advance of the contractual provisions – whilst maintaining a good level of control over current project delivery. Plans for an orderly handover should be developed and a strategy put in place for what happens next, to ensure that contract expiry can be a success.

To achieve this, we believe that there are specific activities that you should undertake, each forming part of the three workstreams.

  • Local Partnerships is a joint venture between the Local Government Association, HM Treasury and the Welsh Government. We provide support to central and local government in resolving contractual and operational issues with PPP and PFI contracts. We contributed to the NAO's report on managing PFI assets and services as contracts end. To coincide with its launch we have produced guidance, available on our website, to support our public sector colleagues considering the expiry of PFI contracts.

Rosie Pearson is corporate director at Local Partnerships

Rosie.Pearson@local.gov.uk

NATIONAL AUDIT OFFICE

Forward motion for SEND?

By Rob Powell | 15 January 2026

Local government funding is a huge talking point as the new year kicks into gear, with cumulative SEND deficits being one of the areas strongly in need of he...

NATIONAL AUDIT OFFICE

EFS: Useful tool, not an end state

By Rob Whiteman CBE | 15 January 2026

Applying for Exceptional Financial Support? February could mark a turning point, as more councils see budgets stretched to breaking point. Rob Whiteman offer...

NATIONAL AUDIT OFFICE

On your marks for the AI era in local government

By Dan Peters | 15 January 2026

Councils are racing to use AI to cut costs and improve services – but a shortage of skills is holding them back and time is running out. Dan Peters reports.

NATIONAL AUDIT OFFICE

Going beyond resilience

By Liam Young | 15 January 2026

Liam Young looks at the true cost of today’s head roles, arguing that now is the time to establish what leadership now looks like, how it is supported and ho...